Community water supply system for drought mitigation

Problem Area - Drought

Created at: 15 May 2022

Description

  1. Rehabilitation of existing cracked spring intake and leaking transmission lines to maximize flowrate available to community

  2. Construction of new 10,000L ferrocement tank to allow community to carefully manage their water during times of drought

  3. Construction of 12 new public tapstands and connections to distribution network through a total of 1800m of pipe, to ensure entire equal access to water within the village

Help us provide more detailed information about this project by contributing!

About the author

Geert Westerhuis

• Submitted 227 projects
• Expert at Water
• Netherlands

View all 227 projects by this author →